Receive, coordinate and distribute complete development proposal applications to Internal Technical Departments and External Technical Agencies/Departments within 1 day.
-
Monitor and coordinate after receiving comments/certificates of development proposal applications from Internal Technical Departments and External Technical Agencies/Departments after distribution as follows :
-
Ensure that every application for development proposals is presented in the One Stop Centre (OSC) Meeting according to the following period :
-
Simultaneous development plan application category I, II, III, IV - 40 days
-
Separate the development plan application Planning Permission Plan, Engineering & Landscape – 40 days and Building Plan application - 30 days
-
Ensure that the Internal Technical Department submits the working papers for committee certification no later than 7 days before the meeting.
-
Collect, coordinate and submit committee certification papers to the meeting secretariat for distribution to Local Central Committee members no later than 3 days before the meeting.
-
Managing and ensuring that Local Central Committee Meetings are held 2 times a month.
-
Ensure that the notification letter of the decision presented in the Local Central Committee Meeting is distributed to the applicant within 3 days .
-
Monitor and ensure the full approval by the Internal Technical Department within 7 days after the Local Central Committee Meeting.
-
Receiving and registering a complete development proposal application at the OSC counter does not exceed one (1) hour.
-
Ensuring that the waiting time to submit a forwarding proposal application does not exceed 30 minutes.
-
Ensuring that the waiting time to get advisory services related to the promotion proposal does not exceed 15 minutes.